Footprint (emprise au sol)
The vertical projection of the volume, overhangs included; a roof overhang without posts does not count (R420-1). A pergola, a carport, a raised deck all have one.
French planning code, re-read in 2026
A project, its measurements and, if you like, the address: the tool gives the formality, the article behind it and the form, taking the local plan’s zone and historic monuments into account.
Answer the questions: the formality appears after the last one.
Each page gives the project’s thresholds, with the tool already set for it.
The vertical projection of the volume, overhangs included; a roof overhang without posts does not count (R420-1). A pergola, a carport, a raised deck all have one.
Enclosed, covered areas with more than 1.80 m of headroom, measured inside the walls. Garages, lofts that cannot be converted and cellars are not included.
To extend a house, the declaration threshold rises from 20 to 40 m² in zone U of a local urban plan — unless the whole then exceeds 150 m², where the permit returns.
The surroundings of a historic monument, a remarkable heritage site, a listed site: the exemptions fall away, and even a 3 m² shed needs a declaration. A registered site only matters for fences and facades.
Compulsory for a permit once the floor area of the whole exceeds 150 m² — for a new house as for an extension (R431-2).
Each formality has its form, to download from service-public. The file is lodged at the town hall of the municipality where the land is, on paper or online.
For building work that does not need a building permit, only a declaration.
The form on service-publicThe procedure step by step (in French)
For a detached house or its outbuildings, beyond the declaration thresholds. Another project, such as a change of use, has its own form: the service-public procedure gives it.
The form on service-publicThe procedure step by step (in French)
Three other tools from the studio serve the same project: the clay in the soil, which can require a soil survey, the VAT rate on the work, and what the registers say about the company before you sign its quote.
Is the land clay?Which VAT rate?Check the company before signing
The thresholds come from the French planning code, read on Légifrance on 12/11/2026: articles R421-1 to R421-17-1 (decrees of 13 November 2024 and 20 February 2026) and R431-2. The forms are those of service-public, checked the same day. The zone and protected areas come from the Géoportail de l’urbanisme (IGN), read at the time of the search.
An information tool, not a decision: only the town hall processes and authorises. Building without the required permission risks a fine and demolition.