Choose your contract’s index, the price, the base month and the revision month: the tool gives the coefficient, the revised price and the two values behind it, published in the Journal officiel.
Revision and updating: what French law says
A revisable price follows a formula written in the contract: an index, a base month — the month the price was set —, a frequency, and sometimes a fixed term, the share of the price that does not move. The French public procurement code provides for it in public contracts (article R2112-13); between private clients and tradespeople, the contract says it, and nothing requires it.
A fixed price does not move, but in a public works contract it is updated once if more than three months pass between the bid and the start of work, at the economic conditions of three months before that start (articles R2112-9 to R2112-11).
The index is chosen by trade: BT01 for an all-trades building, the trade’s own index for a lot — BT32 for a clay-tile roof, BT38 for plumbing. If your contract cites the ING index (engineering), it is in the list too.
BT and ING indices for August 2026
Base 2010, latest values published in the Journal officiel (on 16 October 2026), and their change over a year.
| Index | Value | A year earlier | Over a year |
|---|---|---|---|
| BT01 Tous corps d'état | 139.4 | 133.7 | +4.3% |
| BT02 Terrassements | 148.0 | 137.0 | +8.0% |
| BT03 Maçonnerie et canalisations en béton (sauf ossature, béton armé, carrelage, revêtements et plâtrerie) | 140.7 | 135.9 | +3.5% |
| BT06 Ossature, ouvrages en béton armé | 137.0 | 132.3 | +3.6% |
| BT07 Ossature et charpentes métalliques | 152.8 | 147.0 | +3.9% |
| BT08 Plâtre et préfabriqués | 134.0 | 128.8 | +4.0% |
| BT09 Carrelage et revêtement céramique | 135.3 | 131.1 | +3.2% |
| BT10 Revêtements en plastiques | 142.7 | 137.9 | +3.5% |
| BT11 Revêtements en textiles | 148.2 | 142.5 | +4.0% |
| BT14 Revêtements en plaque de pierre naturelle sciée et produits assimilés | 142.8 | 139.9 | +2.1% |
| BT16b Charpente bois | 146.3 | 139.6 | +4.8% |
| BT18a Menuiserie intérieure en bois | 142.2 | 136.3 | +4.3% |
| BT19b Menuiserie extérieure en bois | 147.1 | 141.4 | +4.0% |
| BT26 Fermeture de baies en plastique y compris fenêtre PVC | 136.3 | 134.3 | +1.5% |
| BT27 Fermeture de baies en aluminium | 148.9 | 139.1 | +7.0% |
| BT28 Fermeture de baies en métal ferreux | 141.3 | 129.8 | +8.9% |
| BT30 Couverture en ardoises de schiste | 153.4 | 148.3 | +3.4% |
| BT32 Couverture en tuiles en terre cuite | 149.3 | 142.3 | +4.9% |
| BT33 Couverture en tuiles en béton | 141.5 | 134.4 | +5.3% |
| BT34 Couverture en zinc et en métal (sauf cuivre) | 151.1 | 139.9 | +8.0% |
| BT35 Couverture en bardeaux bitumés | 154.5 | 146.1 | +5.7% |
| BT38 Plomberie sanitaire (y compris appareils) | 149.4 | 137.6 | +8.6% |
| BT40 Chauffage central (à l'exclusion du chauffage électrique) | 133.5 | 130.1 | +2.6% |
| BT41 Ventilation et conditionnement d'air | 141.0 | 136.0 | +3.7% |
| BT42 Menuiserie en acier et serrurerie | 145.7 | 139.2 | +4.7% |
| BT43 Menuiserie en alliage d'aluminium | 143.7 | 136.8 | +5.0% |
| BT45 Vitrerie - Miroiterie | 153.4 | 149.3 | +2.7% |
| BT46 Peinture, tenture, revêtements muraux | 140.9 | 135.6 | +3.9% |
| BT47 Électricité | 136.2 | 129.3 | +5.3% |
| BT48 Ascenseurs | 144.9 | 133.8 | +8.3% |
| BT49 Couverture et bardage en tôles d'acier nervurés avec revêtement étanchéité | 150.4 | 145.0 | +3.7% |
| BT50 Rénovation - Entretien tous corps d'état | 141.5 | 135.8 | +4.2% |
| BT51 Menuiseries PVC | 136.1 | 132.9 | +2.4% |
| BT52 Imperméabilité de façades | 150.5 | 139.2 | +8.1% |
| BT53 Étanchéité | 145.1 | 133.6 | +8.6% |
| ING Ingénierie | 139.6 | 135.1 | +3.3% |
Sources
Indices taken from INSEE’s macro-economic database on 15 November 2026; articles read on Légifrance on 12/11/2026.
- Public procurement code, article R2112-13 — revisable prices
- Public procurement code, articles R2112-9 to R2112-12 — fixed prices
- INSEE — Building index BT01, base 2010
- INSEE — Macro-economic database (SDMX)
A calculation, not legal advice: your contract’s price clause prevails.